Inspection IDReason for InspectionInspection DateInspection Status 
SIN-00220925 Renewal 04/12/2023 Compliant - Finalized
RegulationLIS Non-Compliance AreaCorrection RequiredPlans of CorrectionCorrection DatePOC Status
2390.61Floors, walls, ceilings and other surfaces shall be in good repair and free of visible hazards. At the time of the inspection, the urinal in the men's bathroom had an "out of order" sign on it. When the licensing representative asked the agency staff why the urinal was inoperable, they were unaware of the specific reasons as to why it was broken, but that it was not operable. The sink located in the men's bathroom had duct tape over a middle section of it, and the same sink had several areas of a red/rust like color in it. At the time of the inspection, there were approximately 2 containers placed in the facility to catch water that would drip from the ceiling. At the time of the inspection there was no water in the containers and water was not dripping from the ceiling. Agency staff reported that the ceiling didn't leak during the winter, but there has been drips recently. Floors, walls, ceilings and other surfaces shall be in good repair and free of visible hazards.The urinal in the Mens restroom will be removed. The sink will be replaced, and the leaks will be repaired in order to remove the bins that were catching water from the program area. 05/26/2023 Implemented
2390.62Sanitary conditions shall be maintained in bathrooms. The bathroom sink located in the men's room had what appeared to be a gray almost black film that coated the entire sink as well went behind the wall of the sink.Sanitary conditions shall be maintained in bathrooms, kitchens, dining areas and first aid areas.The sink was thoroughly cleaned, though some stains remain. The sink will be cleaned with a stronger cleanser to see if the stains can be removed. If this cannot be done, we will be replacing the sink. 05/26/2023 Implemented
2390.71(a)Bathrooms shall be ventilated by operable windows or mechanical ventilation. The men's bathroom had no ventilation at the time of inspection. There was no operable window or mechanical ventilation located in the men's bathroom. There was a cut out in the backwall, but it was not an operable window, and it did not open to the outside.Work areas, dining areas, kitchens and bathrooms shall be ventilated by operable windows or mechanical ventilation.The building owner was contacted regarding adding a vent fan in the mens' restroom. 05/26/2023 Implemented
2390.83(b)-1An employee trained in the operation of the equipment shall check the fire alarm monthly. There was no documentation that a monthly fire alarm checked occurred in October 2022.An employe trained in the operation of the equipment shall check the fire alarm monthly. Fire safety checks are completed after fire drills are held. Fire drills were scheduled for the remainder of the calendar year, with reminders that will alert the staff to the required drill/inspection. 04/28/2023 Implemented
SIN-00163424 Renewal 10/02/2019 Compliant - Finalized
RegulationLIS Non-Compliance AreaCorrection RequiredPlans of CorrectionCorrection DatePOC Status
2390.87Individual #1 restarted Valley Treasures a year after being initially discharged. He started on 04-25-19 and did not have fire safety training until 07-26-19.Staff, and clients as appropriate, shall be instructed upon initial admission or initial employment and reinstructed annually in general fire safety and in the use of fire extinguishers. A written record of the training shall be kept.Fire Safety was added to the admission checklist that program specialists use when a new program participant starts. Documentation will be sent via email for verification. 10/03/2019 Implemented
SIN-00142704 Renewal 10/04/2018 Compliant - Finalized
RegulationLIS Non-Compliance AreaCorrection RequiredPlans of CorrectionCorrection DatePOC Status
2390.81The back exit door to the outside stairs was extremely difficult to open, requiring staff to use their body weight to push it open. Stairways, hallways and exits from rooms and from the facility shall be unobstructed.The building's owner inspected the door on 10/4/18, the day that inspection occurred, and determined that the door frame was bent. He was able to bend the frame back to normal on that same day, allowing the door to open more easily. 10/04/2018 Implemented
SIN-00124145 Renewal 11/15/2017 Compliant - Finalized
RegulationLIS Non-Compliance AreaCorrection RequiredPlans of CorrectionCorrection DatePOC Status
2390.153(5)Individual #1 and Individual #2 both take psychotropic medications to treat symptoms of a diagnosed psychiatric illness. Neither of these individuals have a SEE Plan in their records.A protocol to address the social, emotional and environmental needs of the client, if medication has been prescribed to treat symptoms of a diagnosed psychiatric illness.On 11/16/17, it has been put into effect that every individual in a vocational program within Avenues that takes a psychotropic medication and has been diagnosed with a psychiatric illness will have a SEE plan. This plan will be devised by the Program Specialist assigned to the participant and the plan will be discussed with the Support's Coordinator and updated in the participant's Individual Support Plan. The SEE Plan will only be updated if a medication change has been administered to the participant to treat symptoms of a diagnosed psychiatric illness. The SEE Plan will be reviewed with the participant's staff and team immediately as well as at every annual team meeting. 11/16/2017 Implemented
SIN-00104055 Renewal 12/08/2016 Compliant - Finalized
RegulationLIS Non-Compliance AreaCorrection RequiredPlans of CorrectionCorrection DatePOC Status
2390.156(a)Individual #1 had an ISP Review done on 1/12/16. He didn't have another ISP Review until 4/28/16, which exceeds the 3 month requirement. Individual #2 had an ISP Review done on 12/4/15. He didn't have another ISP Review until 3/22/2016, which exceeds the 3 month requirement. The program specialist shall complete an ISP review of the services and expected outcomes in the ISP specific to the facility licensed under this chapter with the client every 3 months or more frequently if the client's needs change which impacts the services as specified in the current ISP.ISP reviews will be done every 3 months as per the scheduled due date. If the entire team is not able to meet on the due date of the scheduled meeting, Avenues Program Specialist will meet with the participant to review their status on the scheduled date and both will sign and date for documentation. If the team desires to meet after the scheduled date, they may review what took place on the original scheduled date and the team may then sign and date their follow up meeting. 12/08/2016 Implemented
SIN-00240660 Renewal 04/17/2024 Compliant - Finalized
SIN-00201420 Renewal 05/20/2022 Compliant - Finalized
SIN-00082697 Renewal 10/29/2015 Compliant - Finalized
SIN-00066033 Renewal 08/27/2014 Compliant - Finalized
SIN-00053872 Renewal 08/14/2013 Compliant - Finalized