6400.67(a) | The shower wall was missing ceramic tiles in a large area ( approx. 3 feet by 5 feet ) and had a temporary patch covering the area. Staff indicated that Individual #1 pulled the soap tile plus many more tiles off the wall. | Floors, walls, ceilings and other surfaces shall be in good repair. | A bid has been accepted from Northeast Home Improvements, Inc., for a complete remodel of the bathroom. The bathroom will be gutted and the existing shower/tub, vanity, sink and top, toilet, and faucets will all be replaced. All walls will be torn out as will flooring and replaced.
The work is scheduled to begin on March 23, 2015. The Arc Properties Manager, Joe Sepe, is attempting to move that date up, if possible.
Patrick Quinn will be responsible for oversight of the project to its completion.
|
03/01/2015
| Implemented |